Report on the fact-finding mission of the Budgetary Control Committee to Greece 24/25 September 2015 Control of EU funded priority projects shortlisted by ‘’Task Force for Greece”
Summary
Greece has a long history of ill-managed EU-funded projects which have been prolonged or repaid to the EU budget due to delays in their implementation;
The Greek financial crisis aggravated the problem as the weakening economy influenced the projected profitability of the major infrastructural projects (highways, railways, etc.);
The structure of the central administration leads to an unclear division of competency among the various bodies of the central administration;
The Committee was surprised to discover that both the regional and local administration which should be most directly linked to the conducted projects, as they will be the most influenced by the outcome of the project were not at all or only partially involved in many projects; in most cases the projects were decided by the central Greek administration which is far from the local and regional problems linked to the implementation of the project; a clear example is the metro of the city of Thessaloniki, where the construction was decided in Athens without the City of Thessaloniki having a say on the matter; another example is the rehabilitation of Lake Karla by redirecting the water of the Pinios River, without taking into account the local farming community which was dependant on the river;
A weak point in the implementation of EU-funded projects, is the lack of coordination between the various implementing bodies; in case of unforeseen events, this lack of coordination costs money and heavy delays;
The Committee would like to thank the Task Force for Greece and the relevant services of the European Commission for their sound and professional job in giving a helping hand to Greece during the economic crisis, by providing expertise and additional financial input during the
economic crisis in order to soften the blow the crisis had on the implementing EU-funded projects;
Recommendations
One of the major challenges while implementing EU-funded projects in Greece is the centralisation of the country. Many projects lack regional and/or local oversight. Additionally the frequent changes of governments and thus recurring electoral periods, causes the procrastination of decisions, resulting in unnecessary delays therefore adding another hurdle
to the list of problems the projects have to deal with;
Some of the projects lacked realistic planning - which included rational possible delays due to unforeseen circumstances which are based on similar projects conducted in a similar environment;
One of the most important issues which caused delay in nearly all of the visited projects was the archaeological excavations; while conducting any project which includes ground works in a country as rich in history as Greece, one should include a realistic estimate for delays caused by excavations of archaeological findings; additionally the process of deciding of what to do with the findings once unearthed should be smoother and shorter as it significantly hampers the implementation of the projects;
Another major obstacle is the problem of the expropriation of land; although this remains aprerogative of the Member State, the Committee suggests the Greek authorities consider examining some of the solutions already in place in other Member States in order to eliminate this hurdle which is blocking the timely finalisation of most major projects in Greece;
The Committee would like to remind the Greek authorities that for the 2007-2013 programming period, the eligibility period for expenditure ends on 31 December 2015. After that date, uncompleted projects will have to be funded by the national budget; this includes all of the visited projects, as none of them will be completed and operational by that date;
The Committee would like to remind that if the projects are not fully completed and operational within the operational programme’s set deadline, financial recovery to the EU budget will be applied. we urge the Commission to provide us with an overview of the state of play of each project financed with EU money;
Although the Committee received assurances by the Greek authorities about their financial capacity in finishing these projects by the end of the 2007-13 programming period, it would ask the Greek authorities to provide information on the amounts of national funds reserved in the national budget for the projects to be completed;
The Committee plans to revisit Greece in the upcoming 3-4 years in order to see whether progress has been made in them implementation of projects and whether the appropriate use of EU funds can be noted.
Introduction
Greece has a long history of EU-funded projects, which were not fully completed within the given timeline and had to either be prolonged or paid back. The Budgetary Control Committee decided to send a delegation to Greece in order to try to better understand the source of the Greek problems.
The Committee analysed the 181 priority projects highlighted by the “Task Force for Greece” of the European Commission as problematic. After a careful selection procedure, seven have been chosen for in-field examination. They were:
the construction of the Thessaloniki metro (1200 mln EUR of EU funds),
the rehabilitation of the Karla Lake (42 mln EUR),
the construction of Central Greece (E65) motorway - part Xiniada-Trikala (900 mln EUR),
the completion of the new double high-speed railway line Tithorea-Lianokladi-Domokos (930
mln EUR),
the e-ticket system in Attica (35 mln EUR),
the Greek cadastre (28 mln EUR)
the Greek national register (42 mln EUR).
Situation of Greece following the 2009 economic crises
The magnitude of the economic and social crisis in Greece represented a huge challenge, not only for the Greek population and their political leaders, but also for the European Union. The EU Member
States and the EU institutions expressed their solidarity and support in the form of loans (based on economic adjustment programmes), grants from EU Structural and other funds, and private sector debt write-offs.
So far, Greece has agreed to EU financial assistance in the form of three economic adjustment programmes: the first and second made available EUR 240 billion for the period 2010-2014 and the third (for which the Memorandum of Understanding (MoU) was signed on 19 August 2015) paves the way for mobilising up to EUR 86 billion over three years (2015-2018).
The EU budget supported Greece in the form of grants for an amount of EUR 42 billion during the period 2007-2013 and made available EUR 35 billion for the period 2014-2020.
The EU private sector involvement in debt write-offs accounts for around EUR 100 billion.
Implementation of EU funds for Cohesion policy
The European funds for Cohesion Policy (European Regional Development Fund - ERDF, European Social Fund - ESF and Cohesion Fund - CF), which amounted to EUR 20.4 billion for the 2007-2013 programming period and EUR 15.33 billion for the 2014-2020 programming period, are implemented
through Sectoral/Regional Operational Programmes (OP).
For the 2007-2013 programming period an amount of EUR 20.4 billion was allocated for the Cohesion policy (ESF: EUR 4.36, ERDF: EUR 12.15, CF: EUR 3.69). The ESF budget for 2007-2013 allocated EUR 4.36 billion finances 4 OPs: education and lifelong learning (EDULLL), human resources development (HRD), public administration reform (AROP) and national contingency reserve (NCR).
Task Force for Greece
The Task Force (TFGR), created within the European Commission in July 2011 in a close dialogue with Greek authorities, identified and coordinated the technical assistance which Greece needed in order to implement structural and institutional reforms and facilitate the absorption of EU funds. TFGR
work focused on fostering economic growth, while raising competitiveness and employment. It provided regular progress reports to the Greek authorities and to the European Commission. The Task
Force was based in Brussels with an office in Athens.
The activities of the TFGR have been various:
a) Expert missions & workshops to share the best practice and expertise, e.g. up to July 2014, TFGR has arranged over 400 missions, including 35 policy workshops;
b) Support through small value contracts to finance experts working with the Greek authorities over a period of 3-4 months to evaluate, design or implement reforms, e.g. up to March 2014, 52 such contracts were arranged by the TFGR;
c) Continued support from international organisations;
d) Domain leadership - where a Member State could become a ‘domain leader’ in a policy area, e.g. France volunteered to be a domain leader in the area of central administration reform while at the regional level it was Germany. TFGR was financed through resources available in the Technical Assistance (TA) budget of the European Commission. A budget of EUR 18.3 million in commitments and EUR 12.8 million in
payments has been managed by the TFGR for TA needs in Greece. Sometimes national experts provided short term assistance were paid by their home countries.
The top priority policy areas for reforms were: Administrative Reform, Tax Policy, Revenue Administration, Public Financial Management (especially expenditure control), the Health Sector, the Business Environment, and Social Security Reform. In 2011, the OECD undertook an evaluation of
central and tax administration in Greece and produced findings which served as a basis for the Technical Assistance (TA) of administrative and tax reforms.
With its administrative and budgetary decision on 17 June 2015, the European Commission has modified the Establishment Plan of the Secretariat General by creating a new service ‘the Structural
Reform Support Service’ - which integrated the team and structure of the Task Force for Greece and became operational on 1 July 2015. The new service provides know-how to any Member State requesting it and, in particular, it will support Greece with the implementation of administrative and structural reforms - including assistance with the use of European Structural Funds.
181 projects of the Task Force for Greece
In October 2011 a list of 181 priority projects was agreed upon between the Commission and the Greek administration. The projects were of major significance for the country’s development, would have a high impact on Greek economy, and would enhance job creation and employment. The total budget for the priority projects amounted to EUR 11.5 billion (the total Greek NSRF budget amounted to EUR 24 billion). These projects should prove to be a key driver for absorption. The aim was to
produce visible results, boost the economy & competitiveness, and create employment.
The main problems encountered during implementation were:
Delays at maturation stage
Delays in licensing
Dissolution of contracts due to lack of liquidity of contractors
Lengthy court appeals during awarding procedures.
The Greek authorities have reinforced the process of implementation for the priority projects with the use of project managers, Jaspers assistance, and close follow-up. To this extent, several technical meetings took place between the European Commission and the Greek authorities to review the priority projects at risk and to discuss the bottlenecks, measures to be taken, and their timetable, as well as assess the progress achieved so far in the context of the severe shortage of liquidity faced during the last months.
As of 30 September 2015:
70 out of 181 priority projects have been completed (total co-financed budget EUR 1.385,74 million)
39 are being implemented on schedule (total co-financed budget EUR 3.346,26 million)
52 projects need to be accelerated (total co-financed budget EUR 5.513,20 million)
14 projects are unlikely to be concluded (total co-financed budget EUR 998 million)
6 project were cancelled (total co-financed budget EUR 275 million)
Projects visited by the delegation
1. Construction of the Thessaloniki metro
Red Line Basic Project under construction
Blue Line 1 South-east Extension to Kalamaria under construction
Blue Line 2 – Yellow Line North-west Extension to Stavroupoli and Papageorgiou Hospital under planning
and design
Yellow Line West Extension to Evosmos under planning and design
Green Line Extension to the airport under planning and design
Description
The full project includes the completion of the
main line of the Thessaloniki metro with its 13
stations. The main objectives of the
Thessaloniki Metro Main Line include the
upgrade of the transport infrastructure of the
city of Thessaloniki, the gradual decongestion
of city traffic, and the increased use of public
transport.
The investment contributes in reducing primary
and secondary pollutants in the atmosphere,
improving the quality of life in Thessaloniki, and indirectly enhancing road safety. The Main Line of the
Thessaloniki Metro also contributes in boosting competitiveness of local enterprises and in creating
over 470 employment opportunities during implementation and around 390 permanent jobs during
operation.
8
The project under actual examination is
Phase A’ of the Thessaloniki Metro Main Line
(Project 2) forming part of the wider
Thessaloniki metro project aiming at
constructing a driverless metro system in the
city of Thessaloniki. Overall it includes both
the Main Line (9,6 km with 13 stations) and
the eastern Extension to Kalamaria (4,8 km
with 5 stations) which is a different project in
itself.
The 2007-13 programming period contains both a bridge and a phasing project. Initiated in the
framework of OP Roads in 2000-2006, it continues in 2007-2013 as the project funded via the OP
Macedonia-Thrace, but is managed through the MA of OP Accessibility and will be concluded via OP
Infrastructures 2014-2020. The completion and operation of the Main Line is estimated to serve
approximately 22 500 new journeys daily during rush hour.
Total eligible expenditure: EUR 1,2 billion
Bridge project: EUR 196 million in 2000–06 and EUR 279 million in 2007-13
Phasing project: EUR 117 million in 2007-13 and EUR 610 million in 2014-20
EU support 2007-2013
The decisions for the co-financing are
C(2014) 8749 of 18.11.2014 and
C(2014) 8745 of 18.11.2014.
Eligible public expenditure declared up
to now to Commission services:
270.386.963,52€
2007-2013 Eligible co-financed public
expenditure (EUR)
EU Contribution (EUR)
2013GR161PR009
(bridge)
213 825 600 181 751 760
2013GR161PR010
(phase)
89 604 736 76 164 026
Total 303 430 336 257 915 786
9
State of play
Still national funds are required in 2015-16 to complete the bridge project: EUR 82 000 000 (of which
EUR 59 000 000 eligible, under the condition that the works are implemented by end of 2015).
Issues at stake
Currently works are not progressing. Implementation progress for bridge project is at 86,82% and for
the phasing project it’s at 58,67%. The contractor requested to dissolve the contract last December.
Attiko Metro wishes to extend the current
contract, therefore, a committee is set up and
the negotiations are ongoing.
The stop of the work affects the absorption of
the OP Macedonia-Thrace. The bridge-project
from 2000-06 will burden the national funds
because it cannot be phased to 2014-2020,
while a modification request for phasing the
2007-2013 decision should be made.
Scenarios currently under negotiation by Attico Metro:
Continuation of works with the same contractor with an objective to complete the project, by 2018
excluding Venizelou station (due to archaeology issues) which can be completed by 2020.
Re-tender the remaining works and complete the project with a new contractor.
Further development of the situation after the mission took place
Agreement now expected to be concluded at the end of November 2015, greatly reducing the
possibility of additional eligible expenditure up to end-December 2015.
Ministry of Culture’s decision to alter the terms of the Venizelou station construction very likely to
create additional issues on the construction of the station; consequences currently under
examination by the European Commission.
The question is whether the most important station - Venizelou, will be constructed due to the
archaeological findings.
10
2. Rehabilitation of the Karla Lake
Description of the project
This project is located in Thessaly ,
the financially biggest environmental
project in the Balkans. Its objective is
to rehabilitate Karla Lake as an
important natural site as the water
and natural resources of the region.
Initially the project faced important
management issues and was
contested by local farmers claiming
for subsequent indenisation with
regard to risk of limitation of irrigation.
The re-naturalisation of part of a
previously drained lake will raise the dangerously low groundwater level in an entire region. Surface
water and new groundwater sources will enable farmers to irrigate their fields. The nearby city of Volos
will be supplied with drinking water from groundwater sources. A nature protection and tourist area will
be created.
Planned functioning of the project
The lake will be filled with water from the
Pinios River and rainwater. Water from
the Pinios River will be diverted to Lake
Karla via a system of channels (dug out
and not lined with concrete). (The system
of channels was created several decades
ago after the area was drained, as a
source of water in droughts and an outlet
for water in case of floods). Rainwater
from the surrounding mountains will also flow into the lake through a new system of lined channels.
Newly installed pumps will discharge water into
the lake in the event of flooding.
Development of a system of groundwater
sources
All illegal groundwater sources in the area are to
be closed as far as possible. In their place,
hundreds of interlinked new sources will be
created. These will bring water to the city of
11
Volos and provide farmers with additional
water for irrigation in times of drought.
EU support 2007-2013
This project is a bridge project from the 2000-2006 programming period. For 2007-13, the
EC Decision was adopted on 29.8.2011
(C(2011)6067) under the OP Environment &
Sustainable Development 2007-2013, Priority
Axis 2 ERDF.
Eligible co-financed public expenditure: EUR 47.363.588 million.
EU contribution: EUR 37.890.870 million.
Eligible public expenditure declared up to now to Commission services: EUR 19.686.213,66 million.
State of play
The project should be properly completed and become operational by the closure of the period 2007-2013. Being a bridge project from 2000-2006, it cannot go beyond the 2007-13 period. The managing
authority has confirmed by end of May 2015 that the project will be completed within the 2007-13
programming period, except 3 out of the 10
subprojects will not be implemented. However,
these 3 subprojects do not affect the
implementation of the project.
An amount of 28 million EUR is lacking to finish
the project.
Current situation, stage reached in the Lake
Karla project
1. The reinforced part of Lake Karla (dams,
channels, pumps, overflow areas) is largely complete.
2. After having been at a standstill for years, work is now again underway on the rainwater
drainage and collection system.
3. Some tourist sites (such as the local history museum) have been completed, while others (such
as sealed cycle paths and leisure centres) are still left outstanding.
4. Water has once again been flowing from the Pinios River through the channels into the lake. At
present, the lake has no large expanses of water, and there are only a series of puddles. Local
environmental experts estimate that, if the volume of water entering the lake remains the same,
it will take two years for the planned, ecologically stable water level in Lake Karla to be reached.
5. Water quality in Lake Karla is poor, having been made toxic as a result of the problem with
farming, illegal tips, and the low level of replenishment. Experts from the universities in Volos
and Thessaloniki report regular waves of fish deaths. At the same time, the water poses risks
12
for people‘s skin and health. Under
WHO rules, the lake should be secured
against public access.
6. The illegal wells used by farmers
remain in operation. Accordingly, the
new system of groundwater sources
has only been partially embarked on. It
is therefore impossible to say when the
city of Volos will receive any drinking
water (particularly since the
groundwater level must first rise and this will take years, even when the lake is full).
7. The problem of illegal rubbish remains. They are not being removed, and neither are the
farmers being prevented from creating new ones. ‘Sustainable farming’ is still a foreign concept.
8. De facto control over the channels leading away from the Pinios River is in the hands of the
farmers’ association. It does not believe in the project’s success; therefore, farmers have been
independently extracting water for their fields and have blocked the river from reaching the lake
for more than a decade. All the relevant local authorities are aware of this.
9. Properly functioning water management is a decisive factor in the project‘s success. Until now,
this has never been seriously discussed or organised among those involved. The conflict of
interests between the groups named as beneficiaries in the EU project description has erupted
into a dispute that has still not been resolved.
10. Acting on behalf of the government in Athens, the regional governor has been responsible for
the EU project since January 2014. He has been pressing ahead with the construction work.
Core problems affecting the
project
1. The underlying aims of the
project cannot be achieved with the
measures planned in the EU
project. Even when filled to the
optimum level, Lake Karla will
scarcely be capable of restoring
the normal groundwater level in the
whole region, supplying everyone
with drinking water, and providing irrigation water for all the region’s farmers. It appears unlikely
that it will be able to function as an ideal local recreational area. Given the extensive amount of
agriculture in the region, local scientists doubt whether it will ever be possible to achieve good
water quality in the lake.
13
2. The project requires perfect coordination
between all the relevant ministries,
government bodies, local interest
groups, politicians, authorities and
citizens. This has never been seriously
attempted since the project was
launched. Measures that were easy to
implement have been taken. This mainly
involves construction work. Crucial
management measures, particularly
water management and consultation with farmers, have still not been put in place.
3. The highly centralised ministries and government bodies leave regional representations with few
powers and few financial possibilities at the local level. As a result, mistakes and misguided
measures that have been recognised at local level are not acted on, and the necessary
countermeasures are not taken. Athens must decide, but the authorities in Athens have no
money, are in no hurry, or have no idea and respond only to short-term political events.
14
3. Construction of Central Greece (E65) motorway - part Xiniada-Trikala
Description
The Central Greece Motorway (E65) (Lamia - Karditsa - Trikala - Kalambaka - Egnatia Highway) forms
part of the TransEuropean Network – Transport (TEN-T) and is the backbone of Central Greece’s
transport infrastructure. It is expected to make a very significant contribution to the safety of road travel
and transport and reduce accidents by at least 80%, all while allowing faster and cheaper travel.
The construction of Motorway E65 will also help end the isolation of Central Greece (due to poor
transport links) and improve connections between Western Macedonia and Epirus, thereby making
Albania and FYROM better accessible; therefore it is likely to boost regional development, tourism and
freight traffic in an area with a special potential for further economic development, while at the same
time helping to reduce the unemployment rate and increase per capita income.
This project will also play an
important international role
because it is linked via the
Egnatia Highway and its vertical
axes with Albania and FYROM
and, by extension, the other
north-western Balkan countries
and further beyond..
The Central Greece Motorway
E65 has a total length of
15
approximately 175 km and a four lane
cross-section and a width of 23.30 m
or 22.00 m (in difficult sections)
(according to Decision of Minister for
the Environment, Regional Planning
and Public Works 8938/30/10/08), with
two lanes and an emergency lane in
each direction and a central
reservation.
The concessionaire is responsible for
the studies and the construction, operation, maintenance and exploitation of the motorway.
The concessionaire is also responsible for operating, maintaining and exploiting the section of the
PATHE Motorway from Skarfia (KP 183 +300) to Raches (KP 240 +300) (Maliakos Kolpos’ horseshoe
bend), which is 57.2 km in length.
Problems occurred
Due to the economic crisis in Greece, which has resulted, inter alia, in a dramatic reduction in the
volume of traffic and a significant decline of projected revenue for the project as well as an increase in
funding costs, lending banks stopped funding the project in the spring of 2010.
This led to work on the Motorway E65 project – and the other Concession Agreement Motorways –
being suspended in February 2011. After lengthy negotiations between the Greek government, the
concessionaire and the lending banks, in November 2013 an agreement was reached to amend the
Concession Agreement, which was ratified by the Hellenic Parliament. The Agreement provides for the
commencement of work on the Xyniada -Trikala Section on 20.12.2013 with a view to completion on
31/12/2015, while the completion of the respective sections (a) Lamia - Xyniada and (b) Trikala Egnatia Motorway have been referred for review at an unspecified time after 2015.
As a result, the project, as modified by the amendment (reset) of the Concession Agreement and as it
is being constructed today, concerns
the Xyniada -Trikala section
(approximately 79km).
Main elements of the Reset
Concerning four motorway
concessions that are currently built in
Greece, and following the
unprecedented financial crisis, the
Greek State chose to restore the
concession’s viability through a
16
renegotiation of the concessions’ terms among the Greek State, the concessionaires and the banks.
This operation is referred to as the “Reset”. The terms of the Reset have in principle been agreed
between the State, the concessionaires and the banks. The agreements were signed end-2013. Main
elements of the reset for these four motorways are:
- a reduction of physical outputs (length of the motorways) on two out of the four motorways, mainly
due to the annulment by the Greek High Court of the environmental permits for certain sections of
the Olympia Odos and E65 motorways and high expropriation costs. In particular, the Patra-Pyrgos
section (Olympia Odos) and the Interchange PATHE – A/K Xyniadas and A/K Trikalon A/K
Egnatias (E-65, the project under examination) are moved to the next programming period (2014-2020), if certain conditions are met. On the other hand, the section Pyrgos-Tsakona (Olympia
Odos) will be constructed in due time.
- an extension of the construction period granting additional revenue earnings from tolls during the
construction period, without, however, extending the concession period;
- state guarantees [within the boundaries of the State’s project revenues] for the concessionaries’
cash flow taking into account a low
case scenario on traffic projections
with any drop in traffic below this
benchmark effectively supported by
the State from its own revenue
share. Any future increase in trafficrevenue would be used to
compensate the state for its
contribution (loan to the project).
EU support 2007-2013
EC Decision C(2013)8215 of 16.12.2013 under the OP Accessibility 2007-2013, Priority Axis Z CF.
Eligible co-financed public expenditure: EUR 670.234.238
EU contribution: EUR 569.699.102.
Eligible public expenditure declared up to now to Commission services: 417.638.155€
State of play
Physical object (contracted): 99%
Implementation of physical object (through MIS): 63% (through independent engineer): 57%
Issues: archaeology, change of alignment, new expropriations for 4 km (none of them are expected to
cause major delays, even though the completion of the project has been rolled from end-2015 to
2016). The project is part of a DAS 2014 audit for the ECoA.
Additional national funds needed to complete the project: none. However eligibility rules (eligibility
ends on 31-12-2015) will not allow for the co-financing of expenses incurred after that date.
Expected end-date: within 2016.
17
Problems affecting the timetable of the project
Archaeology
All regions have had restrictions lifted and rehabilitation work is now being undertaken in regions that
had been subject to restrictions under the supervision of the respective archaeological services.
Expropriations
– For the section from KP 47 + 313 to KP 51 + 183 additional property registers are being drawn up
due to the change in the route undertaken to avoid a site of archaeological interest.
– 5 additional land registers have been declared on orthophotomaps and their approval is pending
– The requisitioning procedures have been completed for three regions and will shortly be delivered
to the concessionaire with the payment of compensation for requisitioning to the beneficiaries.
Environmental Licensing
– For the section from KP 47 + 313 to KP 51 + 183 an Environmental Impact Assessment (EIA) has
been approved.
– For the Xyniada connecting road, an EIA has been submitted for consultation in the Region.
Utilities
– Work is under way to relocate PPC high-voltage pylons in the region of Xyniada.
18
4. Completion of the new double high-speed railway line Tithorea-Lianokladi-Domokos
Description
The project includes the construction of a new double track high speed line Tithorea-LianokladiDomokos, 106 km long, which will be completed and fully operational in 2017. The total budget of the
project, including non-eligible expenses, is 1.700,8 mil. Euro.
The project is located on the Orient/EastMed (OEM) Corridor of the TEN-T core
rail network and in particular on the
Thessaloniki - Athens rail section, which
is part of the axis Vidin – Sofia –
Burgas/TR border Sofia – Thessaloniki –
Athens/Piraeus.
The new railway line has been designed
for speeds of 200 km/h for the section
Tithorea- Lianokladi and 130-160 km/h
for the section Lianokladi- Domokos.
Given that the section Tithorea-Lianokladi-Domokos, is the only section in the Athens-Thessaloniki
axis without a double line equipped with modern signalling and electrification systems, the construction
19
of the project will complete the conversion of the railway line Athens-Thessaloniki into a double track
high speed axis equipped with modern signalling, tele-commanding and electrification systems.
Once this project is implemented, the expected results in the Athens-Thessaloniki axis are:
decrease in journey time by approximately 50 minutes,
improvement in the level of the services provided to the railway users, as well as upgrade in the
services provided by means of the
decrease in the journey time,
the increase in the timetables
frequency,
the improvement in the quality,
comfort and safety of railway
transportation.
It is also expected that the reliability
of the railway will increase and, as a
result, its competitiveness will be
upgraded.
Taking into account that the Athens-Thessaloniki axis is the backbone of the Greek railway network,
the project will contribute to facilitating and promoting international transportation by means of the
railway. At the same time, international freight traffic in the railway network will increase( specifically
combined transport traffic) through the connection between the railway network and the N. Ikonio port
in Piraeus, one of the major freight ports in the Mediterranean, which was completed and put into
operation in 2013.
Moreover, the aim of the global project is the interconnection of the Athens-Thessaloniki and AthensPatras lines and, therefore, of the overall network of Central and Northern Greece, by eliminating the
need to change the traction engine (electric / diesel) at the terminal stations of the section, i.e. Tithorea
and Domokos.
The physical object of the project includes 2 twin tunnels with single track branches with a total length
of 30,837.00 m (Kallidromo and Othris Tunnels), double track tunnels with a total length of 4,499.61 m,
railway bridges with a total length of 6,087 m, and the construction of two new railway stations at
Molos and Agios Stefanos, as well as two
new stops at Aggies and Thavmakos.
Once this project is implemented, the new
electrified double railway line AthensThessaloniki, 500 km long, which complies
with the interoperability specifications for
the core network, will be completed.
The implementing body of the action is
ERGOSE, which is responsible for
implementing OSE’s Investment
20
Programme. OSE (National Railways
Organization) is the railway infrastructure
manager of Greece, responsible for the
management and operation of the national
railway infrastructure.
The present project completes the
infrastructure sections of a project of 106
km of a TEN-T double railway track in the
Othrys mountainous region, which has
been co-financed in three different periods (1994-99, 2000-6, 2007-13). Under the previous
programming period, the project has been supported by EU budget significantly (EU Contribution
612,85 million). With regard to 2014-2020, remaining infrastructure, electrification, signalling and
interoperability may be co-financed from CEF depending on the outcome of the on-going assessment
by the Commission services.
EU support 2007-2013
EC Decision adopted on 22.08.2011 (C(2011)6071) under the OP Accessibility 2007-2013, Priority
Axis H CF and last modified by Decision C(2015)4203 adopted on 17/06/2015.
Eligible co-financed public expenditure: EUR 362.665.959 (initial Decision 474.099.000€)
EU contribution: EUR 308.266.065 (initial Decision EUR 402.984.150)
Eligible public expenditure declared up to Commission services: EUR 418.189.345.
State of play
80% completed all together.
The Greek modification request incorporates a reduction of physical and financial scope of the project,
which has been adopted by C(2011)6071 of 22-8-2011, due the section that follows it and makes it
operational is co-financed by CEF and DG MOVE (period 2014-20). Delays were due to the financial
crisis (constructors declaring bankruptcy), to the lack of a deciding manager due to government
changes as well as the non-foreseeable difficulties for the construction of the two tunnels.
OLAF case- OF/2013/0198
On 25 January 2013, DG REGIO auditors
were informed about an article published
in a Greek newspaper stating: “following
preliminary investigations, the Greek
prosecutor is investigating the co-financed
bridge major project “Lianokladi-Domokos
tunnel construction”.
According to this investigation, there were
21
successive amendments by the concessionaire to the approved study resulting in inflating costs and
released clauses. In addition, there was double-funding of work already invoiced as well as illegally
paid compensations (that should have settled by the contractor or the insurance company).
By letter dated 1 March 2013 (Ares n°271094), the Greek authorities were invited to confirm if the
prosecutor’s investigation does not relate to projects co-funded by the European Union. The Greek
authorities were also invited to inform the European Commission about the declared expenditure up to
now within the framework of the closure of the 1994-1999 and 2000-2006 programmes, as well as if
the current period 2007-2013 does not involve expenses related to the criminal activities under control.
By letter dated 29 March 2013 (Ares n°551325), the Greek authorities informed the EC that the
contract affected by the OLAF case concerned the bridge project and the amounts affected are as
follows:
- Under the period 2000-2006 – EUR 3.077.395,80 - These expenditure has been excluded from the
final payment claim.
- Under the period 2007-2013 – EUR 8.135.124,39 - This amount has been excluded from the
payment claim submitted in July 2013 for the OP “Accessibility” 2007-2013.
For the Tithorea - Lianokladi an OLAF case, OF/2013/0198 was opened in April 2013, after the EC
notification to them on 14.2.2013. The case was closed in October 2014.
Reasons for delays
During the implementation of this major project there have been significant delays due to objective
reasons. The main reasons are listed below:
Severe problems during the excavation of Kallidromo tunnel due to unexpected and extremely
unfavourable geological/geotechnical conditions in the subsoil at the area of the tunnel, which led
to time-consuming procedures in order to address management issues relating to the contracts
for the construction of the tunnel.
Termination of two construction contracts due to the Contractors’ failure to complete the physical
object of these contracts, resulting in the re-tendering of the remaining works with a new contract.
Delay in the approval of the environmental terms for the project in section Lianokladi-Domokos.
The main problem was the reservations
concerning the opinion granted by the
Department of Natural Environment in
the Ministry of Environment, Urban
Planning and Public Works (YPEHODE),
in terms of the project impact on the
“Wolf” habitat, which lives in the area
crossed by the project.
Addressing issues relating to the
interfaces between the new railway line
22
and the alignment of the Ε65 highway, which runs close to the new railway line in part of the
alignment.
Delays during the tendering process of the individual contracts used for the project
implementation. The delays were due to changes in the legal framework for awarding public
works, to claims and appeals filed by the tender participants, etc.
Delays due to government and management changes.
23
5. Greek cadastre
Description
Since the early 19th century Greece operates under the system of Registrations and Mortgages, as a
paper-based public register of real property owners and the deeds that they have been involved in.
This register:
cannot identify or accurately describe individual real properties (position and boundaries)
ensures the publicity of transactions but not legal security
is not complete (e.g. the rights of the State are not registered)
does not allow the identification of the existing owners of a property
The Cadastral project was initiated in the mid 1990’s by the Ministry of Environment, Physical Planning
and Public Works, aiming to replace the existing system of Registrations and Mortgages as a uniform
and always up-to-date system of registrations, which would consist of the geometric description and
the ownership status of all the real properties of the Country, overseen and guaranteed by the State.
The new system combines Cadastre and Land Register.
The cadastral mapping in Greece started in 1995. In 2000-2006 (3rd CSF), the EU Funds (41,5 out of
EUR 83 million of public expenditure) supported the development of the ICT component and the
digitalisation of active property titles in the main urban areas. Note the project was initially co financed
under the 2nd CSF, but due to mismanagement, the EU proceeded with the full recovery of the funds.
24
EU support 2007-2013
A major project was programmed under the 2007-2013 period, but it has not been submitted to the
Commission services. Additional funding is planned to complete the project in the programming period
2014-2020.
State of play
The advancement of the land register is
modest so far. Overall, to date, the state of
progress in the cadastral survey mapping
of estimated 38 million of property titles is
as follows: a) 20 % are completed b) 20 %
are currently tendered and c) the
remaining are still to be contracted out.
The cadastral survey is conducted by means of generations of studies (there are four generation of
studies, namely 1998, 2005, 2011 and 2013). These generations of studies are the basis for the
published tenders.
The EIB Jaspers Facility has been mobilized by the Greek Authorities to assist them to develop a
robust project application including a sound cost benefit analysis.
Problems identified
Given European and international experience in this regard, establishing a land register should not be
a particularly difficult technical feat. Initially, the Greek land register project was prepared in haste and
important parameters were not properly evaluated. The national authorities had difficulty in pursuing a
robust methodology and commitment in adopting the necessary measures for implementing the
project.
It is regrettable that the Commission had to intervene in order to ensure that the necessary legal
provisions on the land register were passed, procedures were modernized, and officials were
recruited.
When problems were noted, neither the final beneficiary nor the public authorities intervened to
remedy matters and a blind eye was turned to serious problems for years, even though the project
costs were meanwhile skyrocketing. This supports the view that the competent authorities failed to
exercise adequate control over the project developments and its evolution.
In short, lack of a clear vision, strategy and objectives are detrimental in taking the project further.
Strong commitment and robust managerial capacities and organisational arrangement are absent.
Many Ministries and stakeholders involved (overlapping of activities) hamper an efficient coordination
and decision making resulting in considerable delays. Complex legislation and time consuming
tendering procedures further hinder the realisation of the project. The failure of 1994 in setting up a
cadastre should be avoided.
25
6. Greek national registry
Description
This project concerns the infrastructure for the creation of the National registry to record and monitor
all new civil status documents currently declared in the local registry offices and the majority of existing
civil records of the country’s registries trough a modern and systematic way.
EU support 2007-2013
This project is not a major project. It was
approved by the managing authority with
eligible co-financed budget of
EUR41.907.342,01 million under OP
Digital Convergence and 4 regional OPs.
State of play
The National Registry project was
approved in April 2009 and tendered in
November 2011 with the first contract signed in 2013. The project was delayed from the very
beginning as there were delays in its final design and the number of contracts to be tendered
(currently 9).
It concerns two components: a) an IT infrastructure including the digitalization of the registrations to
the centralised system and peripheral registries and b) the validation phase of the registration process.
The latter is done by its own means (by
the Ministry staffing). However, as bonus
payment is blocked from the MoU, the
staffing is not proceeding with the
validation. To do so and hence de-block
the project, a Common Ministerial
Decision should be signed between the
Ministry of Interior and the Ministry of
Finance for paying the staff of the
Ministry of Interior (registrars) to
implement by its own resources.
The project, as it stands today, will be
phased to the next programming period. The goal is that the IT system is completed in 2007-2013 and
the productive operation phased to 2014-2020.
We suggest that the project level can take the important decisions and not the central level which is
the case now. Contracts with a value of more than 50 000 EUR still need to be signed. This creates an
artificial bottleneck.
26
7. E-ticket system in Attica
Description of the project
This system will cover and serve all modes of public transport (thermal buses, electric buses, trolley
buses, urban railways-metro, tramways - trams and the suburban railway) operating in the area of
competence of the Athens Urban Transport Organisation (OASA). All paper tickets will be replaced by
electronic tickets, which will be validated by units to be installed in all vehicles. The AFCS will be
completed with entry and exit gates in the metro system.
The project will be implemented and operated through a Public-Private Partnership with a total
duration of 12 years (2 years for the design, installation and 10 years for the full operation of the
system).
The benefits of the new AFCS derive from the users’ time saving, the operational performance, and
the reduction of revenue losses due to fare evasion and from the reduction in the use of passenger
cars.
EU support 2007-2013
EC Decision was adopted on 8.11.2013
(C(2013)7458) under the ROP Attica 2007-2013, priority Axis 2 (ERDF).
Eligible co-financed public expenditure: EUR
34.758.000 million.
EU contribution: EUR 29.544.300 million.
27
State of play
The completion of the first phase of infrastructure implementation is marginal. Management and sound
coordination by the Beneficiary OASA S.A. must be reinforced in order to achieve a completed and
operational phase. The project will be phased to the next programming period.
28
Annex 1
Brussels, 22 September 2015
Fact-finding mission
of the Budgetary Control Committee (CONT)
to Greece
24/25 September 2015
FINAL PROGRAMME
Control of EU funded priority projects shortlisted by ‘’Task
Force for Greece”
Members of the delegation:
1 Ms Ingeborg Gräßle (EPP, DE, Head of Delegation)
2. Mr Tomáš Zdechovský (EPP, CZ)
3. Ms Verónica Lope Fontagné (EPP, ES)
4. Mr Gilles Pargneaux (S&D, FR)
5. Mr Georgi Pirinski (S&D, BG)
6. Ms Inés Ayala Sender (S&D, ES)
7. Mr Anders Primdahl Vistisen (ECR, DA)
8. Mr Igor Šoltes (The Greens/EFA, SL)
Accompanying Members:
9. Ms Eva Kaili (S&D, GR)
10. Mr Miltiadis Kyrkos (S&D, GR)
CONT Secretariat
1. Mr Michal Czaplicki (EP mobile: +32-475/754 668)
2. Mr Hrvoje Svetic (EP mobile: +32-498/983 593)
Advisors of Political Groups
1. Mr Balazs Szechy (EPP)
2. Ms Stefanie Ricken (S&D)
3. Mr Roccu Garoby (The Greens/EFA)
Commission
DG REGIO
1. Mr Stylianos Loupasis, - team leader
2. Mr Antonios Sartzetakis (Thessaloniki Metro, double high-speed railway line TithoreaLianokladi-Domokos, E65, Karla Lake).
29
3. Mr Panayiotis Thanou (cadastre, E-ticket, national registry. He is a desk officer (AD) in
charge of Digital OP).
ECA
Mr Lazaros Lazarou, Member of the European Court of Auditors
Interpreters
FR
Ms Stalia Georgoulis - team leader
Ms Nathalie Paspaliari
EN
Ms Ioulia Spetsiou
Mr Jose Fisher Rodrigu
EL
Ms Maria Provata
Ms Vasiliki Chrysanthakopo
Mr Laurent Recchia - technician, valise
Languages covered
EN, FR, EL
Coordination in Athens - European Parliament Information Office
Ms Maria KAROUZOU - logistics
Mr Leonidas ANTONAKOPOULOS
Head of Information Office of the European Parliament in Greece
(8 Leof. Amalias, Athens, GR-105 57,Tel +30 / 210 327 1011, Fax +30 / 210 331 15 40
E-mail: [email protected])
European Commission Representation
Ms Pascalina Grigoriadou, Mr Panagiotis Alevantis
Head of Representation, European Commission Representation in Greece
(Vassilissis Sofias 2, 106 74 Athens, Greece, E-mail: [email protected],
Tel. +30 2107272133, Fax +30 2107244620)
Transport:
TSOKAS BUS SERVICES
Address: Mesogeion 279, GR – 15231 CHALANDRI
Contact person: Mr Manolis PAPADOGIORGAKIS
Mobile + 30 6970000525
Phone : + 30 2106740440 – 41, Fax: + 30 2106710332
[email protected]
30
Accomodation/Hotels:
hotel ELECTRA PALACE in Thessaloniki
IN 23/9/15 – OUT 24/9/15 – 1 night
9 Aristotelous Square, 54624 Thessaloniki
Tel: +30 2310 294 000, http://electrahotels.gr/en/thessaloniki/electra-palace-thessaloniki/
hotel SAMARAS (3*) in Lamia
IN 24/9/15 – OUT 25/9/15 – 1 night
14, Athanasiou Diakou Street, Lamia
Τel : +0030 22310 28971-3, http://www.samarashotel.gr/
hotel GRANDE BRETAGNE in Athens
IN 25/9/15 – OUT 26/9/15 – 1 night
1 Vasileos Georgiou A’ str., Syntagma Square · Athens
Tel: +30 210 3330000, http://www.grandebretagne.gr/
Flights:
OUTWARD
Flight On From Time
Brussels Thessaloniki
23September via Munich 16.35 - 17.50
19.40 - 22.55
Via Frankfurt 9.05 - 10.10
11.05 - 14.45
Via Belgrade 10.25 - 12.30
13.20 - 15.25
Via Athens 11.45 - 15.55
17.15 - 18.10
RETURN
Athens - Brussels 26September direct Brussels
Airlines
8.35-11.00
Athens - Brussels 25September direct ***End of the
programme
at 18.30***
Brussels
Airlines
17.00-19.30
JETAIR
18.30-21.20
31
Wednesday, 23 September 2015
22:55 Arrival of the delegation at the Thessaloniki airport, bus transfer to
hotel in Thessaloniki
Thursday, 24 September 2015
7:45 Departure from hotel
8:15 Visit of the project “metro of Thessaloniki”
managing authority: Intermediate Managing Authority of the
Operational Programme “Improvement of Accessibility”,
Ms. Z. Papasiopi, [email protected],
Tel: 0030 210 69 30 154
Implementing authority: ATTIKO METRO SA - Thessaloniki Metro
Directorate
Tel: +30 2310 504746
Dr George Konstantinidis, Project Director
Mr Dionysis Panagiotopoulos, Deputy Project Director and
Supervisor in Depot and E&M Works
Mr Yannis Vakalopoulos, Supervisor in Civil Works
Mr Nikos Dellas, Supervisor in Civil Works
Mr Asterios Papaoikonomou, Head of Scheduling and Cost
Control Discipline
Mr Michalis Goniotakis, Head of Contract Discipline
Ms Peny Arampatzi, Deputy Head of Contract Discipline
Mr Theoklis Panagiotidis, Head of Design of Works
Discipline
venue: ATTIKO METRO SA. Thessaloniki Metro Directorate
40 26th Oktovriou Str. (opposite Port Gate 11),
4th floor of ATRINA CENTER building, Thessaloniki
10:00 Departure from Thessaloniki by bus (175 km)
12:30 ‘’Rehabilitation of Karla Lake’’ project + working lunch
Meeting with the Governor of the Thessaly Region,
Mr Konstantinos Agorastos
venue: Farsalon 148 – New Regional Council Hall, Larissa
14:00 Visit of the Lake Karla project
venue: Lake Karla
managing authority: Intermediate Managing Authority of the
Operational programme “Environment & Sustainable
Development”, Mr Nikolaos Mamalougas, [email protected],
Τel: 0030 213 21 42 202 or 0030 213 21 42 295
15:00 Meeting with Ms Ifigenia Kagalou and Dr Sidiropoulos Pantelis,
representatives of Management Body of Ecodevelopment Area of
32
Karla-Mavrovouni-Kefalovriso-Velestino on the environmental
aspects of the Lake Karla project
venue: Lake Karla, Petra pumping station
16:00 Departure to Trikala by bus (120 km)
17:30 Visit of the project “Central Greece (E65) motorway - part
Xiniada-Trikala”
managing authority: Intermediate Managing Authority of the
Operational Programme “Improvement of Accessibility”, Ministry
of Economy, Infrastructure, Maritime Affaires and Tourism
Ms Zoe Papasiopi [email protected]
Tel: +30 210 69 30 154
Mr Zisimos Karvounis, Director
Special Service for construction of projects of Central and
Western Greece, Ministry of Economy, Infrastructure, Maritime
Affaires and Tourism [email protected], [email protected]
Tel:.+30 2106992234 or +3016947904547
venue: construction site of the E65 highway, meeting point in
Trikala, then driving on the newly constructed highway till Xiniada
19:30 Departure from the site of the motorway, transfer to hotel in Lamia
(45 km)
20:30 arrival to the Samaras Hotel in Lamia
venue: 14, Athanasiou Diakou Street, Lamia
Friday, 25 September 2015
7:45 Departure from hotel
8:30 Visit of the project “completion of the new double highspeed railway line Tithorea-Lianokladi-Domokos” in
Kallidromo - site visit of the Kallidromo tunnel - the longest
tunnel in the Balkans (9 km each tube)
Intermediate Managing Authority of the Operational Program
“Improvement of Accessibility”
Ms Maria Oikonomou, [email protected] Tel: 0030
210 67 97 600
Mr. Yiannis Krassopoulos
Ms Alexandra Kalaitzi
ERGOSE
Mr. Ath. VOURDAS, Managing Director
Mr. D. RAPPOS, Project Director
Ms. L. ISSAIA, Consultant to the Managing Director
33
Mr. Ap. TSAKIRIS, Supervisor of Infrastructure Works
Mr. G. KATAKOS, Supervisor of E/M Works
Mr. G TRIFONAS, Assistant Supervisor of Infrastructure
Works
Consortium of the Contractor
Mr. S. KARAVAKIS, Project Director
Mr. Chr. STAVROU, Head of Worksite
venue: entrance to the Kallidromo tunel
10:00 Departure from Kallidromo by bus (175 km)
12:30 Arrival in Athens + working lunch
venue (till the end of the official programme): Information Office of
the European Parliament in Greece, 8 Leof. Amalias, Athens
14:00 Presentation of the project “Greek cadastre”
managing authority: Mr Manolis Giampouras
Intermediate Managing Authority of the Operational Programme
“Digital Convergence”, [email protected],
Tel: 0030 2131-500.539
Mr G. Logothetis The Head of the Special Coordination
Service
Mr M. Yiampouras, Head of the Managing Authority of OP
“Digital Convergence”
Mr I. Kastritis and Mr. V. Dimopoulos, Officers who monitor
the relevant project
Mr. Th. Karoumpalis, Head of the Monitoring Unit of the MA
Ms A. Anagnostaki, Head of Planning Unit of the MA
Prof. Byron Nakos, President, National Cadastre and Mapping
Agency (N.C.M.A.) S.A
Ms Christina Klonari, Managing Director, National Cadastre
and Mapping Agency (N.C.M.A.) S.A,
Dr Dimitrios Rokos, Director of Planning and Investments,
National Cadastre and Mapping Agency (N.C.M.A.) S.A
16:00 Presentation of the project “National Register”
Mr G. Logothetis The Head of the Special Coordination
Service
Mr M. Yiampouras, Head of the Managing Authority of OP
“Digital Convergence”
34
Mr I. Kastritis and Mr. V. Dimopoulos, Officers who monitor
the relevant project
Mr. Th. Karoumpalis, Head of the Monitoring Unit of the MA
Dr Th. Oikonomou, Ministry of the Interior and Administrative
Reconstruction Director General of e-Government and
Elections,
Dr I. Manolitsakis, Chairman of Information Society SA
Mr G. Tsakogiannis, CEO of Information Society SA
Mr S. Boviatsis , Ms K. Papadaki, Ms Z. Kontiza - the team in
charge of the project
Mrs N. Tsouma, Director of Information Society SA
16:45 Presentation of the project “e-ticket system in Attica”
managing authority: Mr Manolis Giampouras
Intermediate Managing Authority of the Operational Programme
“Digital Convergence”, [email protected],
Tel: 0030 2131-500.539
Mr G. Logothetis The Head of the Special Coordination
Service
Mr M. Yiampouras, Head of the Managing Authority of OP
“Digital Convergence”
Mr I. Kastritis and Mr. V. Dimopoulos, Officers who monitor
the relevant project
Mr. Th. Karoumpalis, Head of the Monitoring Unit of the MA
Mr Gregory Dimitriadis, Chairman of the Board & CEO of the
Athens Urban Transport Organisation S.A. (OASA)
Ms Hamsa, Mrs.Mavroudi, Mr. Anastasiadis, Mr. Kypraios the team in charge of the project
17:30 Press conference
venue: Information Office of the European Parliament in Greece,
8 Leof. Amalias, Athens,
***
18:30 End of the programme
35
Annex 2
Total EU contribution paid up to 1.08.2015 per project to be visited by
the EP delegation
Project Name
Amount paid
up to date in
EUR
Metro of Thessaloniki 354 000 000
Extension of Metro of Thessaloniki 28 500 000
Rehabilitation of Karla Lake 27 900 000
Central Greece (E65) motorway part Xiniada-Trikala 442 500 000
Completion of the double high-speed railway line Tithorea-LianokladiDomokos
501 300 000
Cadastre 41 500 000
National Register 5 500 000
E-Ticket System in Attica 0
Note: The only recoveries related to these projects are for the “Cadastre” project. Due to mismanagement the EU proceeded
with a full recovery of funds financed in the period 1994-1999 under the 2
nd
Community Support Framework (CSF). The
recoveries were proposed to be made in two phases: EUR 32 000 000 deducted from the European Regional Development
Fund (ERDF) payments to the Greek authorities as from 31/03/2002 and EUR 25 900 000 deducted from ERDF payments to
Greek authorities as from 31/03/2004
1
1
PV(2001) 1549 final - https://ec.europa.eu/transparency/regdoc/rep/10061/2001/FR/10061-2001-1549-FR-F-0.Pdf
36
Annex 3 181 Priority Projects monitored by the Task Force for Greece (state of play 30 September 2015)
STATUS CODE TITLE SECTOR PROGRAMME REGION
COMPLETED 1 Compressor station at Nea Mesimvria ENERGY
Competitiveness and
Entrepreneurship Central Macedonia
COMPLETED 2 High Pressure Natural Gas Pipeline to Aliveri ENERGY
Competitiveness and
Entrepreneurship Continental Greece
COMPLETED 9
Construction of the building “Ambient Intelligence” for
the Technology Institute COMPETITIVENESS: INNOVATION AND RTD
Crete and Aegean
Islands Crete
COMPLETED 22
Development of a National System of Electronic Public
Procurement - E-Procurement
COMPETITIVENESS: PUBLIC
ADMINISTRATION AND PRODUCTIVITY
THROUGH THE USE OF ICT Digital Convergence All over the country
COMPLETED 25
Integrated Informatics Sytem for the (Tax) Control
Services - (Elenxis)
COMPETITIVENESS: PUBLIC
ADMINISTRATION AND PRODUCTIVITY
THROUGH THE USE OF ICT Digital Convergence All over the country
COMPLETED 32 Central ERP for the Central State Account Department
COMPETITIVENESS: PUBLIC
ADMINISTRATION AND PRODUCTIVITY
THROUGH THE USE OF ICT Digital Convergence All over the country
COMPLETED 38 Ring road of Vathy in Samos TRANSPORT: ROADS
Crete and Aegean
Islands North Aegean
COMPLETED 40 Local road Kampi - Havouna- Kato Meria in Kea TRANSPORT: ROADS
Crete and Aegean
Islands South Aegean
COMPLETED 41 Paraionia Road - Tunnel Junction St Ilia TRANSPORT: ROADS
Western Greece Peloponnese - Ionian
Islands Western Greece
COMPLETED 42 Completion of local road Larissa-Karditsa TRANSPORT: ROADS
Thessaly - Mainland
Greece - Epirus Thessaly
37
COMPLETED 43 Improvement of the local road 40 Paiania - Spata - Loutsa TRANSPORT: ROADS Attica Attica
COMPLETED 44
National Road Thiva-Livadeia km position 9+000 to 11+
600 TRANSPORT: ROADS
Thessaly - Mainland
Greece - Epirus Continental Greece
COMPLETED 45 Road Atalanti- Section E TRANSPORT: ROADS
Thessaly - Mainland
Greece - Epirus Continental Greece
COMPLETED 46
UPGRADE OF ROAD SECTION “EGNATIA ROAD - ANATOLI
JUNCTION” (IOANNINA CITY ENTER) TRANSPORT: ROADS
Thessaly - Mainland
Greece - Epirus Epirus
COMPLETED 51
Completion - improvement of the national road Rodos Lindos TRANSPORT: ROADS
Crete and Aegean
Islands South Aegean
COMPLETED 52 Improvement of local road Ag. Isidoros - Laerma of Rodos TRANSPORT: ROADS
Crete and Aegean
Islands South Aegean
COMPLETED 53 New roadsection of Potamos dam -Pantanassa TRANSPORT: ROADS
Crete and Aegean
Islands Crete
COMPLETED 55 15th Local road of Kalloni-Eressos in Lesvos TRANSPORT: ROADS
Crete and Aegean
Islands North Aegean
COMPLETED 57
CONSTRUCTION OF IGOUMENITSA - PREVEZA ROAD /
SECTIONS UBGRADE (KARTERI – GERAKARI – PARGA) TRANSPORT: ROADS
Thessaly - Mainland
Greece - Epirus Epirus
COMPLETED 58 Completion of the road axis from Serres to Amfipoli TRANSPORT: ROADS Macedonia - Thrace Central Macedonia
COMPLETED 74 Narional Road Larissa-Trikala TRANSPORT: ROADS
Thessaly - Mainland
Greece - Epirus Thessaly
COMPLETED 76 Safety of road network TRANSPORT: ROADS
Crete and Aegean
Islands Crete
COMPLETED 77
Renovation of under and over structure of the ISAP lines
and Omonoia tunnel TRANSPORT: CLEAN URBAN TRANSPORT Attica Attica
COMPLETED 78
Athens metro, extension of line 3, section “EgaleoHaidari”, depot “Eleonas”, transfer station “Xaidari,
transfer station “Keramikos” TRANSPORT: CLEAN URBAN TRANSPORT
Environment Sustainable
Development Attica
COMPLETED 80 New ETHEL buses TRANSPORT: CLEAN URBAN TRANSPORT Attica Attica
38
COMPLETED 83 Transformation and modernisation of Kymi port TRANSPORT: PORTS
Thessaly - Mainland
Greece - Epirus Continental Greece
COMPLETED 84 Upgrade and extension of Mantoudi port TRANSPORT: PORTS
Thessaly - Mainland
Greece - Epirus Continental Greece
COMPLETED 86
Work of Infrastrucure and protection of the harbor at
Paralio Astros, in North Kynouria municipality, in Arkadia
prefecture TRANSPORT: PORTS
Western Greece Peloponnese - Ionian
Islands Peloponessus
COMPLETED 92 Port of Lavrio TRANSPORT: PORTS Attica Attica
COMPLETED 93
Piraeus Port: Cruise ships services (St. Nicholas) and
coastal (Port Alon) TRANSPORT: PORTS Attica Attica
COMPLETED 95
Finalisation of electrification of double railway line in the
part of Ska - Kiato TRANSPORT: RAILWAY
Accessibility
Improvement Attica, Peloponessus
COMPLETED 98
Finalisation of suburban railway of Attiki, part: SKA-Treis
Gefyres TRANSPORT: RAILWAY Attica Athens
COMPLETED 104
Upgrade of the railway line Alexandroupolis-Ormenion,
between Didimoteicho and Marasion TRANSPORT: RAILWAY Macedonia - Thrace East Macedonia & Thrace
COMPLETED 105
Supply :INSTALLATION of remote control system management of drinking water Municipal Company for
Water supply and sewage- Lamia ENVIRONMENT
Thessaly - Mainland
Greece - Epirus Continental Greece
COMPLETED 106
Rehabilitation towards the sea of Krausidona river (rain
water) ENVIRONMENT
Environment Sustainable
Development Thessaly
COMPLETED 107 Rehabilitations in different parts of Pineios river ENVIRONMENT
Thessaly - Mainland
Greece - Epirus Thessaly
COMPLETED 108
Internal water distribution networks of the Municipality
of Kozani ENVIRONMENT Macedonia - Thrace Western Macedonia
COMPLETED 109
CONTSRUCTION OF SWEAGE NETWORK ΑΤ DROSIA
PREVEZA ENVIRONMENT
Thessaly - Mainland
Greece - Epirus Epirus
COMPLETED 110
Replacement - Extension of water supply network of the
south-eastern part of Patras ENVIRONMENT
Western Greece Peloponnese - Ionian
Islands Western Greece
39
COMPLETED 112
New stations and remote control systems in the network
of water supply of the municipality of Serres ENVIRONMENT Macedonia - Thrace Central Macedonia
COMPLETED 114 Rehabilitation of Eshatia torrent next to Fleva street ENVIRONMENT Attica Attica
COMPLETED 115
Internal and external sewerage networks of Vatero of
Kozani Municipality ENVIRONMENT Macedonia - Thrace Western Macedonia
COMPLETED 118
Sewerage network and water treatment plants in
communities of Kozani Municipality ENVIRONMENT Macedonia - Thrace Western Macedonia
COMPLETED 119
Regeneration of the New Seafront of Thessaloniki Section from the Royal Theater to the Sea Sports Clubs ENVIRONMENT Macedonia - Thrace Central Macedonia
COMPLETED 120 Sewage system in Plaka - Elounda ENVIRONMENT
Crete and Aegean
Islands Crete
COMPLETED 121 Construction of rainwater pipelines of Paiania ENVIRONMENT Attica Attica
COMPLETED 122
Completion of internal network of sewages in LeykakionPyrgiotikon-Exosti settlements of Naflio Municipality, in
Argolida prefecture ENVIRONMENT
Western Greece Peloponnese - Ionian
Islands Peloponessus
COMPLETED 123 Sewage of Igoumenitsa ENVIRONMENT
Western Greece Peloponnese - Ionian
Islands Epirus
COMPLETED 126
Completion of the water supply network in
NaflioMunicipality of Argolidas Prefecture ENVIRONMENT
Western Greece Peloponnese - Ionian
Islands Peloponessus
COMPLETED 134
Valorisation and restoration of the regional archeological
monuments of Knossos Palace CULTURE AND TOURISM
Crete and Aegean
Islands Crete
COMPLETED 137
Rehabilitation of monuments in the Castle of Mytilene in
Lesvos. CULTURE AND TOURISM
Crete and Aegean
Islands North Aegean
COMPLETED 149
Kindergarten construction in Agios Athanasios area of
Kozani Municipality HEALTH AND EDUCATION INFRASTRUCTURE Macedonia - Thrace Western Macedonia
COMPLETED 150 Construction of Primary School in Chiliodendri HEALTH AND EDUCATION INFRASTRUCTURE Macedonia - Thrace Western Macedonia
COMPLETED 151 Construction of 15th High School Larissa HEALTH AND EDUCATION INFRASTRUCTURE
Thessaly - Mainland
Greece - Epirus Thessaly
COMPLETED 152
Construction of primary school at Nea Kallikratia,
Halkidiki HEALTH AND EDUCATION INFRASTRUCTURE Macedonia - Thrace Central Macedonia
40
COMPLETED 153
Construction of a building for the Department of Ecology
and Environment of the Technological Educational
Institution *TEI) in Zakynthos HEALTH AND EDUCATION INFRASTRUCTURE
Western Greece Peloponnese - Ionian
Islands Ionian Islands
COMPLETED 154 Construction of Technical Professional School of Thira HEALTH AND EDUCATION INFRASTRUCTURE
Crete and Aegean
Islands South Aegean
COMPLETED 155 2nd high school of Kos HEALTH AND EDUCATION INFRASTRUCTURE
Crete and Aegean
Islands South Aegean
COMPLETED 156
Construction of a new building and modernisation of
existing infrastructure of Chios General Hospital. HEALTH AND EDUCATION INFRASTRUCTURE
Crete and Aegean
Islands North Aegean
COMPLETED 157 School complex (secondary education) in Lamia HEALTH AND EDUCATION INFRASTRUCTURE
Thessaly - Mainland
Greece - Epirus Continental Greece
COMPLETED 158
Construction of a three-floors building at the General
Hospital of Edessa HEALTH AND EDUCATION INFRASTRUCTURE Macedonia - Thrace Central Macedonia
COMPLETED 159
Technical Univercity of Crete) Environmental Engineering
dept) facilities(B Part) HEALTH AND EDUCATION INFRASTRUCTURE
Crete and Aegean
Islands Crete
COMPLETED 160 Completion of the General Hospital of Agrinio HEALTH AND EDUCATION INFRASTRUCTURE
Western Greece Peloponnese - Ionian
Islands Western Greece
COMPLETED 163
Rehabilitation of the building of Aegean University in
Rodos HEALTH AND EDUCATION INFRASTRUCTURE
Crete and Aegean
Islands South Aegean
COMPLETED 165 All-day primary school Gennadiou in Rodos HEALTH AND EDUCATION INFRASTRUCTURE
Crete and Aegean
Islands South Aegean
COMPLETED 168 Reconciliation of professional and family life
HUMAN RESOURCES DEVELOPMENT OP
(ESF) All over the country
COMPLETED 176
Reorganisation of the State towards a more policy
oriented State (Inserted in the OP in 2010 as a project
implementing the MoU provision on the “Functional
Review of the Central Government”) - Legislation
framework ADMINISTRATIVE REFORM OP (ESF) All over the country
COMPLETED 177
Reorganisation of the General Accounting Office of
Greece and established ERPs in all Ministries ADMINISTRATIVE REFORM OP (ESF) All over the country
COMPLETED 179
Study and proposed new procedures for the reduction of
administrative burdens and costs in five areas ADMINISTRATIVE REFORM OP (ESF) All over the country
COMPLETED 180
Reform of budgeting systems, systems management,
account management (including double- entry
accounting) and financial management of hospitals ADMINISTRATIVE REFORM OP (ESF) All over the country
41
NORMAL
IMPLEMENTATION
PROGRESS 5
Pilot exploitation of geothermal field Erateinou of the
municipality of Nestos ENERGY Macedonia - Thrace Eastern Macedonia - Thrace
NORMAL
IMPLEMENTATION
PROGRESS 6
High Pressure Natural Gas Pipeline Ag. Theodoroi Megalopoli ENERGY
Competitiveness and
Entrepreneurship Peloponese
NORMAL
IMPLEMENTATION
PROGRESS 8 Operation “Saving Energy in housing sector” ENERGY
Competitiveness and
Entrepreneurship All over the country
NORMAL
IMPLEMENTATION
PROGRESS 13 NEW KNOWLEDGE FOR EPIRUS COMPETITIVENESS: INNOVATION AND RTD
Thessaly - Mainland
Greece - Epirus Epirus
NORMAL
IMPLEMENTATION
PROGRESS 16
PHASE 2 AID MEASURE FOR THE HELLENIC TECHNOLOGY
CLUSTERS IN MICROELECTRONICS COMPETITIVENESS: INNOVATION AND RTD
Competitiveness and
Entrepreneurship All over the country
NORMAL
IMPLEMENTATION
PROGRESS 33
Construction of OLYMPIA ODOS motorway (Elefsina Korinthos - Patra) TRANSPORT: CONCESSION ROAD PROJECTS
Accessibility
Improvement Western Greece, Peloponese
NORMAL
IMPLEMENTATION
PROGRESS 35
Construction of the Central Greece (E65) motorway - Part
Ksyniada-Trikala TRANSPORT: CONCESSION ROAD PROJECTS
Accessibility
Improvement
Western Macedonia, Thessaly,
Continental Greece
NORMAL
IMPLEMENTATION
PROGRESS 36 Construction of Ionia odos TRANSPORT: CONCESSION ROAD PROJECTS
Accessibility
Improvement
Epirus, Western Greece, Continental
Greece
NORMAL
IMPLEMENTATION
PROGRESS 37 Construction of the Maliakos - Kleidi motorway TRANSPORT: CONCESSION ROAD PROJECTS
Accessibility
Improvement
Central Makedonia, Thessaly,
Continental Greece
NORMAL
IMPLEMENTATION
PROGRESS 48
UPGRADE TAR COVERAGE FROM ELLINIKO JUNCTION TO
KALENTZI TRANSPORT: ROADS
Thessaly - Mainland
Greece - Epirus Epirus
NORMAL
IMPLEMENTATION
PROGRESS 49
Improvement of Kylliki Road - National Road Patra Pyrgos TRANSPORT: ROADS
Western Greece Peloponnese - Ionian
Islands Western Greece
42
NORMAL
IMPLEMENTATION
PROGRESS 54
Completion of western regional road of Egaleo and side
networks TRANSPORT: ROADS Attica Attica
NORMAL
IMPLEMENTATION
PROGRESS 56
Road project “Construction of Kanavari road- ThespiaDomvrena- Thisvi- Prodromos- Crossroad (Domvraina bypass) TRANSPORT: ROADS
Thessaly - Mainland
Greece - Epirus Continental Greece
60
Improvement of the access road to the landfill of the 2nd
Geographical unity of the Perfecture of AitoloAkarnania TRANSPORT: ROADS
Western Greece Peloponnese - Ionian
Islands Western Greece
NORMAL
IMPLEMENTATION
PROGRESS 61
Egnatia Vertical Axis, Thessaloniki (Derveni) - Serres Promachin, finalisation of parts Lachanas - Α/Κ Christou &
Κ. Ampela –Α/Κ Petritsiou TRANSPORT: ROADS
Accessibility
Improvement Central Macedonia
NORMAL
IMPLEMENTATION
PROGRESS 62
Egnatia Vertical Axis, part Koromilia - Ieropigi Krystallopigi TRANSPORT: ROADS
Accessibility
Improvement West Macedonia
NORMAL
IMPLEMENTATION
PROGRESS 63 Egnatia Vertical Axis, part Florina - Niki TRANSPORT: ROADS
Accessibility
Improvement West Macedonia
NORMAL
IMPLEMENTATION
PROGRESS 65
Construction of road network Airport - Fira - Vourvoulio Oia TRANSPORT: ROADS
Crete and Aegean
Islands South Aegean
NORMAL
IMPLEMENTATION
PROGRESS 69
BOAK: Finalisation of the construction and upgradee of
the Cretan Northern Road Axis (BOAK) TRANSPORT: ROADS
Accessibility
Improvement Crete
NORMAL
IMPLEMENTATION
PROGRESS 79
Extension of line 3 of the Athens Metro, part Chaidari Pireas - phase A TRANSPORT: CLEAN URBAN TRANSPORT Attica Attica
NORMAL
IMPLEMENTATION
PROGRESS 87 New port of Patra. 3rd part, phase A TRANSPORT: PORTS
Accessibility
Improvement Western Greece
NORMAL
IMPLEMENTATION
PROGRESS 102
Construction of the second operating phase of Thriassio
Pedio and contruction of Zefirou railway station TRANSPORT: RAILWAY Attica Western Attica
NORMAL
IMPLEMENTATION
PROGRESS 116
UPGRADE OF THE SEWAGE SYSTEM OF PAMVOTIS LAKE
ZONE/ IOANNINA ENVIRONMENT
Thessaly - Mainland
Greece - Epirus Epirus
43
NORMAL
IMPLEMENTATION
PROGRESS 129
Collection, transfer, treatment and disposal of waste
water in Koropi-Peania ENVIRONMENT Attica Attica
NORMAL
IMPLEMENTATION
PROGRESS 132
Equipment for pre-treatment and recycling of urban solid
waste for the Region of Eastern Macedonia - Thrace ENVIRONMENT Macedonia - Thrace Eastern Macedonia - Thrace
NORMAL
IMPLEMENTATION
PROGRESS 133 protection works of Kastoria Lake ENVIRONMENT Macedonia - Thrace West Macedonia
NORMAL
IMPLEMENTATION
PROGRESS 135
Conservation and restoration of the Acropolis
monuments CULTURE AND TOURISM Attica Centre of Athens
NORMAL
IMPLEMENTATION
PROGRESS 140
Rehabilitation of the former custom office of Chania and
transformation into a cultural center CULTURE AND TOURISM
Crete and Aegean
Islands Crete
NORMAL
IMPLEMENTATION
PROGRESS 141
Β΄ Phase of organisa on and exhibi on of pre-historical,
classical and Byzantine findings in Thebes Archeological
Museum CULTURE AND TOURISM
Thessaly - Mainland
Greece - Epirus Continental Greece
NORMAL
IMPLEMENTATION
PROGRESS 143 Construction of the Archaeological museum of Messara CULTURE AND TOURISM
Crete and Aegean
Islands Crete
NORMAL
IMPLEMENTATION
PROGRESS 145 Touristic presentation of the Region of Attica 2007-2013 CULTURE AND TOURISM Attica Attica
NORMAL
IMPLEMENTATION
PROGRESS 146
Rehabilitation of historic centre of Athens and
connection of archeological sites CULTURE AND TOURISM Attica Attica
NORMAL
IMPLEMENTATION
PROGRESS 147
Bringing out into notice Karytaina Castle in Arkadia
prefecture CULTURE AND TOURISM
Western Greece Peloponnese - Ionian
Islands Peloponessus
NORMAL
IMPLEMENTATION
PROGRESS 171
New school (school in the 21th century) - Support schools
with cohesive and reformed educational programme
EDUCATION AND LIFELONG LEARNING OP
(ESF) All over the country
NORMAL
IMPLEMENTATION
PROGRESS 172
Development of a digital school platform and digital
learning materials
EDUCATION AND LIFELONG LEARNING OP
(ESF) All over the country
44
NORMAL
IMPLEMENTATION
PROGRESS 173 Second Chance Schools
EDUCATION AND LIFELONG LEARNING OP
(ESF) All over the country
NORMAL
IMPLEMENTATION
PROGRESS 174
Apprenticeship programs in Tertiary Education
(Universities)
EDUCATION AND LIFELONG LEARNING OP
(ESF) All over the country
NORMAL
IMPLEMENTATION
PROGRESS 175
Promotion of basic and applied research (Thales
programme)
EDUCATION AND LIFELONG LEARNING OP
(ESF) All over the country
NORMAL
IMPLEMENTATION
PROGRESS 181
Integrated plan for the support of entrepreneurial
activities and of the associated employability through
consulting and training actions and the support of
employment in areas suffering from the consequences of
the economic crisis . CONTINGENCY RESERVE OP (ESF) Convergence and phasing out regions
ADDITIONAL
MEASURES
REQUIRED 3 Energopolis - Kozani ENERGY Macedonia - Thrace West Macedonia
ADDITIONAL
MEASURES
REQUIRED 4
2nd Liquified Natural Gas (LNG) Terminal Upgrade at
Revithoussa Island (3rd Tank) ENERGY
Competitiveness and
Entrepreneurship Attica
ADDITIONAL
MEASURES
REQUIRED 7
Cyclades interconnection with the high voltage (HV)
national interconnected transmission system ENERGY
Competitiveness and
Entrepreneurship Cyclades Islands; Peloponese
ADDITIONAL
MEASURES
REQUIRED 10 Digi Content COMPETITIVENESS: INNOVATION AND RTD Digital Convergence All over the country
ADDITIONAL
MEASURES
REQUIRED 11 Digi Retail COMPETITIVENESS: INNOVATION AND RTD Digital Convergence All over the country
ADDITIONAL
MEASURES
REQUIRED 12 New Buildings of technological institute of Patra COMPETITIVENESS: INNOVATION AND RTD
Western Greece Peloponnese - Ionian
Islands Patras
ADDITIONAL
MEASURES
REQUIRED 15 New Innovative Entrepreneurship COMPETITIVENESS: INNOVATION AND RTD
Competitiveness and
Entrepreneurship All over the country
45
ADDITIONAL
MEASURES
REQUIRED 17
«COOPERATION» SUB-ACTION Ι:«Small and Medium
Scale Cooperative Projects», SUB-ACTION ΙΙ:« Large Scale
Cooperative Projects» 1st Call, 2009 COMPETITIVENESS: INNOVATION AND RTD
Competitiveness and
Entrepreneurship All over the country
ADDITIONAL
MEASURES
REQUIRED 18
COOPERATION 2011 - Collaborative research between
private and public entities focused on specific scientific
and technological areas. COMPETITIVENESS: INNOVATION AND RTD
Competitiveness and
Entrepreneurship All over the country
ADDITIONAL
MEASURES
REQUIRED 19
JEREMIE GREECE and Entrepreneurship Fund (TEPIX ETEAN)
COMPETITIVENESS: ENTERPRENEURSHIP
FOR SMEs
Competitiveness and
Entrepreneurship All over the country
ADDITIONAL
MEASURES
REQUIRED 20
Outturn (Extroversion)-Competitiveness of Enterprises
(Extroversion-Business Competitiveness)
COMPETITIVENESS: ENTERPRENEURSHIP
FOR SMEs
Competitiveness and
Entrepreneurship All over the country
ADDITIONAL
MEASURES
REQUIRED 21 Manufacturing under new conditions
COMPETITIVENESS: ENTERPRENEURSHIP
FOR SMEs
Competitiveness and
Entrepreneurship All over the country
ADDITIONAL
MEASURES
REQUIRED 26
Development of services and infrastructure on spatial
data for the protection of forests and forest lands
COMPETITIVENESS: PUBLIC
ADMINISTRATION AND PRODUCTIVITY
THROUGH THE USE OF ICT Digital Convergence All over the country
ADDITIONAL
MEASURES
REQUIRED 27
Development of an electronic prescribing system and
relevant supporting services (E-Prescription)
COMPETITIVENESS: PUBLIC
ADMINISTRATION AND PRODUCTIVITY
THROUGH THE USE OF ICT Digital Convergence All over the country
ADDITIONAL
MEASURES
REQUIRED 30 Rural broadband
COMPETITIVENESS: PUBLIC
ADMINISTRATION AND PRODUCTIVITY
THROUGH THE USE OF ICT Digital Convergence Rural Areas
ADDITIONAL
MEASURES
REQUIRED 31 E-ticket
COMPETITIVENESS: PUBLIC
ADMINISTRATION AND PRODUCTIVITY
THROUGH THE USE OF ICT Digital Convergence Attica
ADDITIONAL
MEASURES
REQUIRED 34
Construction of the MOREAS ODOS motorway (Korinthos
- Tripoli - Kalamata and Lefktro-Sparti branch) TRANSPORT: CONCESSION ROAD PROJECTS
Accessibility
Improvement Peloponese
ADDITIONAL
MEASURES
REQUIRED 50
Finalisation of Egnatia Vertical Axis, Komotini - Nymfea Greek-Bulgarian borders TRANSPORT: ROADS
Accessibility
Improvement East Macedonia and Thrace
46
ADDITIONAL
MEASURES
REQUIRED 59 Construction of a by- pass road at the Corfu Airport area TRANSPORT: ROADS
Western Greece Peloponnese - Ionian
Islands Ionian Islands
ADDITIONAL
MEASURES
REQUIRED 64 Larissa by pass TRANSPORT: ROADS
Thessaly - Mainland
Greece - Epirus Thessaly
ADDITIONAL
MEASURES
REQUIRED 66
Construction of a road section from Potidea to
Kassandria on the road network of Kassandra, Halkidiki TRANSPORT: ROADS Macedonia - Thrace Central Macedonia
ADDITIONAL
MEASURES
REQUIRED 67
Improvement of the road from Gytheio to Areopoli to
Gerolimenas in sections in the prefecture of Lakonia TRANSPORT: ROADS
Western Greece Peloponnese - Ionian
Islands Peloponessus
ADDITIONAL
MEASURES
REQUIRED 68
NOAK: Finalisation of the construction of the part Ag.
Varvara - Ag. Deka (Kastelli) (pos. 22+170 - pos. 37+900)
of the verical road axis Irakleio - Messara TRANSPORT: ROADS
Accessibility
Improvement Crete
ADDITIONAL
MEASURES
REQUIRED 70
Completion of the connections of the PATHE motorway
with the port and the city of Patra TRANSPORT: ROADS
Accessibility
Improvement Western Peloponessus
ADDITIONAL
MEASURES
REQUIRED 71
Construction of road connection of the area of Aktio with
the Western Axis of North-South TRANSPORT: ROADS
Accessibility
Improvement Epirus
73
Completion of the road section from Patrida to Naoussa,
on thw road axis Veria - Naoussa - Skydra TRANSPORT: ROADS Macedonia - Thrace Central Macedonia
ADDITIONAL
MEASURES
REQUIRED 82 Westward extension of tram to Piraeus TRANSPORT: CLEAN URBAN TRANSPORT Attica Athens
ADDITIONAL
MEASURES
REQUIRED 89 Katakolon port TRANSPORT: PORTS
Western Greece Peloponnese - Ionian
Islands Peloponnesus
ADDITIONAL
MEASURES
REQUIRED 90
Gytheio Harbour, in Anatoliki Mani Municipality, in
Lakonia Prefecture TRANSPORT: PORTS
Western Greece Peloponnese - Ionian
Islands Gythio
ADDITIONAL
MEASURES
REQUIRED 94 Completion of Makedonia Airport TRANSPORT: AIRPORTS
Accessibility
Improvement Central Macedonia
ADDITIONAL
MEASURES
REQUIRED 96
Preparatory Works for the construction of the new
double railway line Athens (SKA) – Patras at the section
Rododafni - Rio and electrification of section KiatoRododafni TRANSPORT: RAILWAY
Accessibility
Improvement Western Greece, Peloponnesus
47
ADDITIONAL
MEASURES
REQUIRED 97
Completion of the new double highspeed railway line
Tithorea-Lianokladi - Domokos TRANSPORT: RAILWAY
Accessibility
Improvement Continental Greece
ADDITIONAL
MEASURES
REQUIRED 99
Finalisation of installation of modern signalisation,
telecommand and telecommunications on the PATHEP
axis TRANSPORT: RAILWAY
Accessibility
Improvement
Central Macedonia, Thessaly,
Continental Greece
ADDITIONAL
MEASURES
REQUIRED 100
Construction of the new double railway line Athens (SKA)
- Patras in the section Diakopto - Rododafni TRANSPORT: RAILWAY
Accessibility
Improvement Western Greece
ADDITIONAL
MEASURES
REQUIRED 111 Closure and rehabilitation of remaining illegal landfills ENVIRONMENT
Environment Sustainable
Development All over Greece
ADDITIONAL
MEASURES
REQUIRED 113
Waste Transfer Station (TS) of Thessaloniki Northwestern
Metropolitan Area ENVIRONMENT Macedonia - Thrace Central Macedonia
ADDITIONAL
MEASURES
REQUIRED 117 Urgent anti-flood works of Xiria river ENVIRONMENT
Thessaly - Mainland
Greece - Epirus Thessaly
ADDITIONAL
MEASURES
REQUIRED 124 Solou river restoration ENVIRONMENT Macedonia - Thrace West Macedonia
ADDITIONAL
MEASURES
REQUIRED 125 Replacement of the central water mains of Zakynthos ENVIRONMENT
Western Greece Peloponnese - Ionian
Islands Zakynthos island
ADDITIONAL
MEASURES
REQUIRED 128
Efficient management of waste water in 120 small
agglomerations, priority C (2.000 - 15.000 inhabitants) ENVIRONMENT
Environment Sustainable
Development All over Greece
ADDITIONAL
MEASURES
REQUIRED 131 Utilization and Promotion of Polyfyto Lake ENVIRONMENT Macedonia - Thrace West Macedonia
ADDITIONAL
MEASURES
REQUIRED 136 Enlargement of the Lefkada canal CULTURE AND TOURISM
Western Greece Peloponnese - Ionian
Islands Lefkada island
ADDITIONAL
MEASURES
REQUIRED 138
Re-creation and restoration of the royal Necropolis and
the Palace of Aegai at Vergina, phase C CULTURE AND TOURISM Macedonia - Thrace Central Macedonia
ADDITIONAL
MEASURES
REQUIRED 142 New Museum of Vergina CULTURE AND TOURISM Macedonia - Thrace Central Macedonia
48
ADDITIONAL
MEASURES
REQUIRED 144
Submarine museums and diving parks in Alonnisos ans
Skopelos CULTURE AND TOURISM
Thessaly - Mainland
Greece - Epirus Thessaly
ADDITIONAL
MEASURES
REQUIRED 148 Alternative Tourism CULTURE AND TOURISM
Competitiveness and
Entrepreneurship All over the country
ADDITIONAL
MEASURES
REQUIRED 161
CONSTRUCTION OF A MULTIDYNAMIC CENTER FOR
TREATMENT OF ALKOHOLISM AND DRUG KRISIS HEALTH AND EDUCATION INFRASTRUCTURE
Thessaly - Mainland
Greece - Epirus Epirus
ADDITIONAL
MEASURES
REQUIRED 162
CONSTRUCTION OF FILIATES HOSPITAL NEW EMERGENCY
DEPARTMENT HEALTH AND EDUCATION INFRASTRUCTURE
Thessaly - Mainland
Greece - Epirus Epirus
ADDITIONAL
MEASURES
REQUIRED 164
Upgrade of the central building of Patras General
Hospital-Agios Andreas and the provision/installation of
medical and hotel equipment HEALTH AND EDUCATION INFRASTRUCTURE
Western Greece Peloponnese - Ionian
Islands Western Greece
ADDITIONAL
MEASURES
REQUIRED 167
Upgrading of the mechanisms for the monitoring of
undeclared labour
HUMAN RESOURCES DEVELOPMENT OP
(ESF) All over the country
ADDITIONAL
MEASURES
REQUIRED 169
A. Drafting of the institutional, regulatory, administrative,
and fiscal context for the promotion of social economy
and the facilitation of the establishment and operation of
social enterprises. B. Development of Social Economy for
the employment of vulnerable groups
HUMAN RESOURCES DEVELOPMENT OP
(ESF) All over the country
ADDITIONAL
MEASURES
REQUIRED 170
A. Local Employment Schemes, adapted to the needs of
the local labour markets (TOPSA) B. Local actions for the
social inclusion of vulnerable groups (TOPEKO)
HUMAN RESOURCES DEVELOPMENT OP
(ESF) All over the country
PROJECT AT RISK 14 Educational Astronomical Park Orliakas COMPETITIVENESS: INNOVATION AND RTD Macedonia - Thrace West Macedonia
PROJECT AT RISK 23 Digital School
COMPETITIVENESS: PUBLIC
ADMINISTRATION AND PRODUCTIVITY
THROUGH THE USE OF ICT Digital Convergence All over the country
PROJECT AT RISK 24 National Registry
COMPETITIVENESS: PUBLIC
ADMINISTRATION AND PRODUCTIVITY
THROUGH THE USE OF ICT Digital Convergence All over the country
PROJECT AT RISK 28 Cadastre
COMPETITIVENESS: PUBLIC
ADMINISTRATION AND PRODUCTIVITY
THROUGH THE USE OF ICT Digital Convergence All over the country
49
PROJECT AT RISK 39
Improvements in the national road of Chios Cardamila in
Chios. TRANSPORT: ROADS
Crete and Aegean
Islands North Aegean
PROJECT AT RISK 47 Road project “Raptaioi Road- New Styra- Styra” TRANSPORT: ROADS
Thessaly - Mainland
Greece - Epirus Continental Greece
PROJECT AT RISK 72
Vertical Axis of Egnatia Ardanio - Ormenio: Sections
Ardanio - Mandra and Mandra -Psathades TRANSPORT: ROADS Macedonia - Thrace East Macedonia & Thrace
PROJECT AT RISK 75
Improvement - Widening of Provincial Road Velo Stimagka - Koutsi - Nemea TRANSPORT: ROADS
Western Greece Peloponnese - Ionian
Islands Peloponnesus
PROJECT AT RISK 81 Metro of Thessaloniki TRANSPORT: CLEAN URBAN TRANSPORT Macedonia - Thrace Central Macedonia
PROJECT AT RISK 85 Construction of pier in Symi port TRANSPORT: PORTS
Crete and Aegean
Islands South Aegean
PROJECT AT RISK 101
Construction of railway line deviation on the line
Thessaloniki - Idomeni, on the section from Polykastro to
Idomeni (part B) TRANSPORT: RAILWAY Macedonia - Thrace Central Macedonia
PROJECT AT RISK 103 Suburban train section Piraeus-3 Gefyres TRANSPORT: RAILWAY Attica Athens
PROJECT AT RISK 127 Rehabilitation of Karla lake ENVIRONMENT
Environment Sustainable
Development Thessaly
PROJECT AT RISK 139 Construction of a Theatre in Zakynthos town CULTURE AND TOURISM
Western Greece Peloponnese - Ionian
Islands Ionian Islands
CANCELLED 29
Integrated Informatics System for the Manager of the
Greek Electrical Grid
COMPETITIVENESS: PUBLIC
ADMINISTRATION AND PRODUCTIVITY
THROUGH THE USE OF ICT Digital Convergence All over the country
CANCELLED 88 New port of Igoumenitsa, phase C TRANSPORT: PORTS
Accessibility
Improvement Epirus CANCELLED 91 Port of Mytilene in Lesvos TRANSPORT: PORTS
Crete and Aegean Islands North Aegean CANCELLED 130 Solid waste managment facilities ENVIRONMENT Attica Attica
CANCELLED 166 Construction and Equipment of Komotini Hospital in new
building with 200 beds HEALTH AND EDUCATION INFRASTRUCTURE Macedonia - Thrace Eastern Macedonia - Thrace CANCELLED 178 Consultant for the implementation of measures against tax evasion and the achievement of sustainable tax compliance ADMINISTRATIVE REFORM OP (ESF) All over the country